code assessable

How long does it take to get a development approval?

Almost all developments (no matter the size of the project) will begin by obtaining development approval (DA) from Council. But how long can this take?

Well, how long is a piece of string? You'll hear the horror stories of a DA taking 12 months to gain approval and almost never hear about the ones that only took a week. The timeframe of a DA can really depend upon the complexity of the application, what level of assessment it is(i.e. Code/Impact Assessable) and how many referral agencies it might have. In this article, I explore the standard timeframes associated with a normal development application in Queensland (timeframes will change between state/territory regions).

Code Assessable development application can be expected to take 45 business daysbefore Council issues a decision notice. This timeframe may be longer if Council makes an Information request (up to 3 months) and does not include the time for your town planner to prepare the lodgement documentation.

An Impact Assessable DA has a similar timeframe to a Code Assessable application but includes a 15 business day public notification period (with up to 10 business days in addition for Council to 'assess' any submissions). That is, up to 70 business days.

I have put the statutory timeframes in the below table for you to better understand the process (inclusive of a general 5-10 business day preparation time for your town planner). Please note that timeframes are subject to statutory requirements under the DA Rules, which Council, the Applicant and third parties must abide by. As such, it is very rare that a DA will take longer than the below timeframes:

town planning approval timeframes


As you can see, the DA process can take anywhere between 2 weeks and 4 months in accordance with the statutory timeframes. Once you have obtained your approval, under the Planning Act 2016, a Development Permit (Approval) issued is valid for a 6 year period.

Can it be faster than 9 business days ever? Yes. Most Local Government Areas (LGA) within Queensland will have a fast-tracked process most commonly referred to as 'RiskSMART'. With this process, the majority of Councils will guarantee a 5-business day turnaround for 100% compliant applications. This is because the town planning consultant will prepare all of the approval package just to be 'signed off' by Council. Not everything can be assessed through the RiskSMART process but it is always a good idea to ask your consultant if it is a potential avenue for your DA.

Any feedback or questions, feel free to post a comment.